做MIGO的PO收货时候过不了,应该怎样做才能过
Material 10+70D has status Costing in Process in plant CC-D
Message no.M7092
Diagnosis
In the material master record,the material status (field
"MAT/PPC status") has been maintained.This means that use of the material can
be restricted.
System Response
Depending on the status,the system issues either a warning message or an
error message.
Procedure
If the message is a warning message,press ENTER to continue processing.
If the message is an error message,you cannot post the transaction.

已提交,审核后显示!提交回复

共2条回复
笑而不答心自闲 共回答了22个问题 | 采纳率86.4%
后台物料主数据里面做了限制了(MAT/PPC字段里做了维护,这个肯定是人为原因不让用这个物料了,比方说是个过期物料,但又不愿意在系统中删除) 找关键用户或顾问查一下为什么要限制这个物料.
靠你自己前台操作做不过去的
1年前
liuhaiyang_1 共回答了13个问题 | 采纳率69.2%
有,在PO的item上,存的时候在EKBE-CHARG
以上回答你满意么?
1年前

相关推荐

在SAP MM模块中MRP3这个view中设置 Consumption mode:2 Bwd/Fwd consumpti
在SAP MM模块中MRP3这个view中设置 Consumption mode:2 Bwd/Fwd consumption per.:45 有什么意义呢?
流泪的猫咪1年前1
千修修修 共回答了12个问题 | 采纳率66.7%
这个是和STRATEGY GROUP配合使用的. 表明消耗独立需求的方式.
向后消耗是表示需求冲减未来的独立需求, 反之, 向前消耗是表示需求冲减过去的独立需求.

一般情况下, 有用SO冲减独立需求的, 也可以DN出货冲减独立需求的, 视你设定的STRATEGY GROUP而定.
网上很多关于STRATEGY GROUP的文档, 可以找来看看.